Interpretation

The difficulties in drafting and interpreting contracts have been illustrated by many cases during 2021

There were surprisingly few appellate judgments during 2021 that considered the impact of Covid19 on the performance of contractual obligations. One such case, however, was the decision of the NSW Court of Appeal in Dyco Hotels Pty Ltd & Ors v Laundy Hotels (Quarry) Pty Ltd1. Although a frustration argument was not pursued on appeal, the court did need to consider the impact of Covid on a hotel vendor's obligation to 'carry on the Business in the usual and ordinary course as regards its nature, scope and manner' until completion of the sale. Did the vendor comply with this obligation when public health orders restricted the operation of the hotel to being a small takeaway business? That is, to what extent should changes in the regulatory context be considered when deciding what is the 'usual and ordinary course'? There was no simple answer: although one appellate judge thought the vendor did comply with this obligation (having regard to what was usual during the period of the relevant public health orders), the majority disagreed. Although the vendor would not be liable for damages for breaching this obligation (given that compliance would have been illegal), the non-compliance meant that the vendor was required to refund the deposit and could not compel the purchaser to complete the contract.

In recent years, there has been much judicial consideration of the implied term of co-operation and related implied terms. Sometimes, however, parties include express obligations to a similar effect. For example, in Rankin Investments (Qld) Pty Ltd & Anor v CMC Property Pty Ltd & Ors2 the Queensland Court of Appeal considered obligations 'to take all necessary steps … to give full effect to the provisions of this Agreement' and 'not to do or cause or permit to be done any act, matter or thing whereby in any way the continued enjoyment of the Land for the purposes of the Joint Venture might be jeopardised'. The case is a good example of courts giving provisions of this type a broad, commercial application.

The failure of a party to comply with a time period specified in the contract is a frequent source of contract disputes. If the failure is a breach of contract, there may be a dispute as to whether the other party is entitled to terminate. Subject to the terms of the contract, the mere failure to comply with a time period does not usually entitle the other party to terminate. This is sometimes described as time not 'being of the essence'. Conversely, the failure of a party to exercise a right within the time specified – such as not exercising an option within the specified time – generally will prevent the power being exercised; in this context, time is 'of the essence'.

In Chevron (TAPL) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd3 the Western Australian Court of Appeal considered whether a party could initiate a price review, despite failing to do so within the contractually specified time. Consistently with other cases concerning the exercise of rights, rather than the performance of obligations, the court found that time was 'of the essence'. The reasoning of the court suggests, however, that the right/obligation distinction will not necessarily be determinative of disputes as to whether time is of the essence.

When heads of agreement envision a future, more detailed contract being entered into, then the heads of agreement itself could be characterised as:

  • a non-binding agreement;
  • a binding agreement to negotiate a more detailed contract (but not otherwise binding); or
  • a binding agreement that will continue to operate even if a more detailed agreement cannot be agreed.

The heads of agreement itself should make this clear. If not, then disputes will arise such as that considered by the NSW Court of Appeal in AMA Group Limited v ASSK Investments Pty Limited4. In that case, the trial judge found that the heads of agreement was itself a binding agreement to sell a business, and that a condition precedent of board approval was only a condition precedent to the entry into a more detailed agreement (and was not a condition precedent to the sale of the business). The Court of Appeal disagreed, and held that the heads of agreement was only a binding agreement to try to negotiate a sale agreement, and that board approval was a condition precedent to any sale proceeding. These issues could have been resolved by clearer drafting, although there is always the possibility that the ambiguity in the agreement reflected a compromise between the parties when negotiating the heads of agreement.

Definitions are an essential tool in most commercial agreements. In theory, a definition should work so that each occurrence of the defined term can be replaced by its definition. In practice, a literal, complete insertion of the defined term often does not work. One method for dealing with this problem is to state that definitions apply 'unless the context otherwise requires'. This can, of course, lead to disputes as to whether the context does otherwise require – one such dispute came before the Queensland Court of Appeal in CS Energy Limited v GPS Power Pty Limited & Ors5. The court's judgment shows a willingness to take a commercial approach in determining when the context 'otherwise required'. Of course, in an ideal world parties would only use definitions where the entire definition can be inserted in place of each use of the defined term.

The use of surrounding circumstances when interpreting contracts continues to be an issue considered by appellate courts in Australia. In Ulladulla Creative Images Pty Ltd v Tibbles6 the NSW Court of Appeal confirmed the basic principles that, when interpreting a contract:

  • a court may sometimes have regard to objective surrounding circumstances known to the parties that assist in identifying the purpose or object of the transaction; but
  • a court may not have regard to the parties' statements reflecting their actual intentions and expectations.

In so far as the trial judge did have regard to evidence of a party's subjective intention in interpreting the agreement, this would have been an error. However, the court ultimately came to the same conclusion about how the contract should properly be interpreted.

The court also noted that evidence of matters known to the parties could be considered for the purpose of ascertaining the subject matter of the contract. The court therefore had regard to such evidence in determining what was 'the claim made against the Company's insurers' (the proceeds of which were to be shared among the parties).

Dyco Hotels Pty Ltd & Ors v Laundy Hotels (Quarry) Pty Ltd [2021] NSWCA 332

Contractual interpretation – termination of contract – COVID-19 – interpretation of clause in sale of hotel and associated business requiring business to be conducted in its '… usual and ordinary course… until completion' – whether an implied term to the effect that the obligation limited to the extent permitted by law – severance of contractual terms

In this case, the New South Wales Court of Appeal considered whether a vendor's termination of a contract for the sale of a hotel and associated business, which was affected by the COVID-19 pandemic, was valid.

The court (2:1) held that termination was invalid, on the basis that the vendor had defaulted on a provision requiring it to maintain the hotel business in its 'usual and ordinary course' up until completion, and therefore the vendor was not entitled to call on the purchasers to complete.

This case is an important example of the application of a standard clause in a sale of business agreement to the consequences of the COVID-19 pandemic.

Facts

On 31 January 2020 Dyco Hotels and Quarryman Hotel Operations (Quarryman) entered into an agreement with Laundy Hotels to purchase a hotel and associated business known as the 'Quarryman's Hotel' in Pyrmont, Sydney. Relevantly, the contract provided that:

  • settlement of the sale and purchase of the business assets would take place on 30 March 2020, and the settlement of the purchase of the property, licence and gaming machine entitlements take place on 31 March 2020;
  • if completion did not take place on the relevant completion date, a party that was ready willing and able to complete and not in default, could serve the other party with a notice requiring completion not less than 10 business days after the date of that notice and making time of the essence (a notice to complete); and
  • until completion, Laundy was required to, '… carry on the Business in the usual and ordinary course as regards its nature, scope and manner…' (clause 50.1).

On 23 March 2020 the Public Health (COVID-19 Places of Social Gathering) Order 2020 came into effect. The order, which was made under the Public Health Act 2010 (NSW), relevantly provided that pubs must not be open to the public except for the purpose of selling food and beverages for persons to consume off the premises (the First Public Health Order). On 14 May 2020 a substitute order was made: the Public Health (COVID-19 Restrictions on Gatherings and Movement) Order (No 2) 2020. The order relaxed the restrictions somewhat by providing that, in addition to selling food and drink for consumption off the premises, licensed premises could sell food or drink to not more than 10 persons at any time but only if liquor were sold ancillary to food service.

From 30 March 2020 up to the date on which the contract was terminated, the Quarryman Hotel sold craft beer from a takeaway window but food was only offered on select days because demand was minimal. Evidence adduced at trial showed that alcohol sales for April were a little over $11,000 and food sales a little over $1,000, while in May alcohol sales were just over $7,000 and food sales were around $750. During this period, the hotel managed to retain only six staff, compared with the 20 staff that were employed before the institution of the First Public Health Order.

On 25 March 2020 solicitors for Dyco and Quarryman wrote to Laundy, asserting Laundy was not ready, willing and able to complete the contract because of an ongoing breach of clause 50.1. On 27 March 2020 Laundy's lawyers responded, stating that compliance with that obligation was rendered illegal due to the First Public Health Order and that the provision was severable under the terms of the contract. Following further correspondence, on 28 April 2020, Laundy served on Dyco and Quarryman a notice to complete. The same day, Dyco and Quarryman commenced proceedings seeking a declaration that the contract was frustrated; a declaration that Laundy was not entitled to issue a notice to complete; or, alternatively, a declaration that while the First Public Health Order was in force and the business was not trading as a going concern, Laundy was not ready, willing and able to complete the contract and not entitled to issue a notice to complete.

At first instance, the court held that: the contract was not frustrated; Laundy had validly served a notice to complete; Laundy had not defaulted on its obligation to carry on the business in the usual and ordinary course; and Laundy was entitled to terminate the contract due to the repudiation of Dyco and Quarryman. Dyco and Quarryman appealed this decision to the Court of Appeal

Judgment

The court considered three main issues.

  • The first issue was the construction of Clause 50.1 and the obligation that the business was to be carried on '… in the usual course of things' until completion.
    • The court affirmed that the clause was to be construed by what a reasonable person would understand it to mean. This means consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or object to be served by the contract.
    • According to the majority of Chief Justice Bathurst and Justice Brereton, the primary judge erred in construing the clause as obliging Laundy to only carry out the business in the usual and ordinary course as regards its nature, scope and manner, so far as it was permitted to do so according to law.
    • Factors that, in the opinion of the majority, supported the conclusion such a restriction was not within the objective intention of the parties included:
      • warranties in the contract that emphasised the importance of the licence permitting the trading activities to be carried on;
      • the lease provided an express obligation for the tenant to keep the premises open during the usual hours of trading; and
      • that under the contract, risk passed from the vendor to the purchasers on completion, not on exchange.
    • For similar factors as listed above, the majority also rejected assertions that a contractual term to the effect that the business needed only to be carried on to the extent permitted by law should be implied into the contract.
    • By contrast, Justice Basten, in dissent, considered that it was reasonable to infer that it was within the parties' expectations the business was one that would be carried on lawfully, and therefore would have rejected the appeal on this ground.
  • The second issue was whether clause 50.1 should be severed.
    • The severability provision in the contract set out that where any court considered any part of the contract was void, voidable, illegal or otherwise unenforceable, or the contract itself would be rendered as such unless the relevant part of the contract were severed, then that part would be severed.
    • Although no formal application was made for clause 50.1 to be severed, the majority indicated they would have rejected such an application, for the following reasons:
      • the public health orders only rendered clause 50.1 unenforceable on a temporary basis. The severability provision did not operate to effect temporary severances;
      • Clause 50.1 was indivisible, as it formed an essential part of the property and hotel business to be transferred to Dyco and Quarryman as a going concern; and
      • the contract allocated to the vendors the risk of supervening illegality before completion.
  • The third issue was whether Laundy was entitled to issue the notice to complete and terminate the contract.
    • The primary judge's conclusion that the contract was not frustrated was not challenged by either party.
    • The question therefore remained whether Laundy was entitled to demand completion in circumstances where it was, in the opinion of the majority, unable to deliver possession of the hotel as a going concern.
    • The majority ruled that as Laundy was unable to convey the hotel licence and other assets as a going concern at the time of the notice to complete and termination (due to the effect of the First Public Health Order), the notice to complete and resulting termination was invalid. This was both because Laundy:
      • could not be considered to be ready, willing and able, a necessary pre-condition for serving a notice to complete at common law; and
      • Laundy was in default of Clause 50.1. Not being in 'default' was an express pre-condition to notices to complete.
    • In the words of Justice Brereton, 'the Vendors were in no position to convey that subject matter to the Purchasers: they could convey only a modified, reduced, and scaled-down version.'
    • Chief Justice Bathurst also rejected Laundy's alternative argument that Dyco and Quarryman had repudiated the contract by asserting that the contract was frustrated. His Honour reasoned that Dyco and Quarryman, while incorrect on the issue of frustration, were correct in asserting that they were not required to complete the contract due to Laundy not being ready, willing and able.
    • Justice Basten, in dissent, opined that clause 50.1 was not a condition precedent, either at common law or as defined under the contract. As such, his Honour considered Laundy to have been entitled to have issued the notice to complete and to terminate the contract.

Rankin Investments (Qld) Pty Ltd & Anor v CMC Property Pty Ltd & Ors [221] QCA 156

Construction – obligation not to jeopardise enjoyment of the land for the purposes of a joint venture; construction – whether obligation to take all necessary steps to give effect to an agreement also prevents acts inconsistent with that agreement

In this case, the Queensland Court of Appeal considered an appeal from a finding of the Queensland Supreme Court that the appellants had breached terms of a joint venture agreement, entitling their fellow 'joint venturer' to buy them out. The terms found to have been breached in the lower court involved obligations upon the parties not to jeopardise 'the continued enjoyment of the land for the purpose of the Joint Venture' and to take all necessary steps to give effect to the agreement.

The court dismissed the appeal, and held that the appellants had breached their obligations to take all necessary steps to give effect to the agreement and/or to ensure continued enjoyment of the land for the joint venture. The notice of event of default, allowing buyout under the agreement, was therefore valid.

The decision shows the willingness of courts to enforce clauses that are expressly intended to facilitate the conduct of commercial endeavours.

The decision also highlights that obligations to take all necessary steps to effect an agreement will usually, and perhaps predictably, prevent conduct contrary to that agreement.

Facts

The parties to the dispute were in a joint venture to redevelop the Big Pineapple on the Sunshine Coast. This joint venture took the form of a company, Big Pineapple Corporation Pty Ltd, as trustee for the Big Pineapple Unit Trust (BPUT). The joint venture comprised:

  • the appellants, Mr Rankin and his company, Rankin Investments (Qld) Pty Ltd, with a 50% interest in the BPUT (Rankin Interests); and
  • the first respondent, CMC, which was controlled by Mr Kendall and Mr Ahern and collectively also had a 50% interest in BPUT (Kendall Interests, collectively with Rankin Interests, the joint venturers).

Under their agreement, the joint venturers agreed that Big Pineapple Corporation would 'lease, licence, and/or develop and/or ultimately dispose of the Property or do any other act, matter or thing as the Board may determine from time to time' (clause 2.1). The board was therefore made responsible for the project on behalf of the joint venture and its decisions would bind the joint venture (clause 5.4)

The Big Pineapple Corporation resolved to advance the development and engage several entities to assist, including for finance, contract tender, securing tenants and surveying. However, in late December 2019, Mr Rankin emailed these entities unilaterally and, in varying terms, told them to cease work indefinitely. The email thread forwarded by Mr Rankin revealed a dispute between the joint venturers to these third parties.

Subsequently, in early 2020, following the contractual process, a notice of event of default was served on the Rankin Interests. It triggered provisions within the joint venture agreement that entitled the Kendall Interests to buyout the Rankin Interests.

At first instance, the appellants, the Rankin Interests, challenged the validity of the notice of event default, arguing that they had not breached the joint venture agreement. This primarily turned on alleged breaches of clauses 6.1(a) and 6.1(c) of the agreement, which provide that each of the parties undertakes with the other:

  • 6.1(a): 'to take all necessary steps on its part to give full effect to the provisions of this Agreement'; and
  • 6.1(c): 'not to do or cause or permit to be done any act matter or thing whereby in any way the continued enjoyment of the Land for the purposes of the Joint Venture might be jeopardised'.

The challenge to the notice was unsuccessful and so the Rankin Interests appealed to the Queensland Court of Appeal.

Judgment

The court unanimously dismissed the appeal and held that the notice of event of default was valid. Necessary for that conclusion was a finding that the Rankin Interests had breached the joint venture agreement. The Justices' reasoning for this conclusion varied:

  • Justice Applegarth, providing the primary reasoning referred to by the other two Justices, found that clauses 6.1(a) and (c) had been breached;
  • Appeal Justice Bond agreed with the orders proposed by Justice Applegarth but would have instead based the conclusion on the breach of clause 6.1(a) (and did not consider it necessary to decide whether clause 6.1(c) had been breached); and
  • President Sofronoff agreed with the reasons of both Justices and thus found breaches of both clause 6.1(a) and (c).

Clause 6.1(c)

The construction of clause 6.1(c) was significant in this case, as the conduct of the Rankin Interests in instructing the third parties to cease work did not directly bear upon the land on which the Big Pineapple sits.

Justice Applegarth was the only Justice to address clause 6.1(c). He found that the actions of the Rankin Interests in instructing the third parties to cease works amounted to a breach of clause 6.1(c). Importantly, in reaching this conclusion, he rejected a more narrow reading of that clause, that it would only limit actions that impaired the availability of the land for the joint venture. Instead, it was emphasised that the commercial and contractual context of 'continued enjoyment' extended to 'development with a view to leasing areas and possibly disposing of the property'. Instructing the third parties to cease works was thus found to be incompatible with this enjoyment of the land.

Clause 6.1(a)

The construction of clause 6.1(a) was also relevant as an alternate basis upon which the notice of event of default could be based.

Justice Applegarth elaborated on two possible routes to the conclusion that the clause had been breached. First, he addressed the question of whether the positive obligation within the clause 'to take all necessary steps … to give full effect to the provisions of the Agreement' gave rise to a negative corollary: that one must not take steps contrary to the agreement. Justice Applegarth addressed several arguments from the appellants that this negative corollary could not exist and dismissed contentions that:

  • the express terms of clause 6.1(a) prevented the existence of such a term;
  • the negative stipulations in other sub-paragraphs of clause 6.1, including clause 6.1(c), evidence an intention that the negative stipulation would not exist;
  • the implication of such a negative stipulation was precluded by an entire agreement clause found within the joint venture agreement; and
  • the negative stipulation was inappropriate, as whether something was inconsistent with the agreement was subject to an uncertain subjective lens.

Justice Applegarth dismissed these arguments, finding that the negative stipulation was not covered by the wording of clause 6.1(a) but could, and should, be implied. In doing so, the primacy of the parties' plain intentions was emphasised. Thus, the agreement was breached by taking a step incompatible with giving effect to it – interfering with the resolutions of the Big Pineapple Corporation.

However, Justice Applegarth, joined by both other Justices, also articulated an alternate path of reasoning to the same result. The simpler and shorter reasoning involved an inquiry into whether the Rankin Interests had taken 'all necessary steps' to give effect to the agreement. It was found that they had not, by virtue of not implementing the resolutions of the company to engage the third parties.

Finally, the court also dismissed a request for leave to argue a new point that the conduct of Mr Rankin was not conduct of the 'joint venturers' under the agreement, as it would have required consideration of further evidence.

The appeal was therefore dismissed and the notice of event of default found to be valid.

Chevron (Tapl) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd [2021] WASCA 193

Construction of contract – whether time stipulation in price review clause is essential – whether notice initiating a price review given outside the stipulated time period is effectual – presumption that time is not of the essence

The Court of Appeal (WA) considered a contractual dispute between Chevron and Pilbara, concerning whether:

  • a time stipulation for notice within a price review clause was of the essence;
  • notice for such a price review given outside this time period was effectual; and
  • a presumption should be made that time is not of the essence.

The court held that when considering the construction of a price review clause in a long-term contract, time is of the essence and that the power to initiate a price review can only be invoked by giving notice within the notice period.

This case provides clarity on the interpretation of price review clauses, emphasising the need for companies to comply with specified time stipulations. More broadly, it also provides guidance on the principles of construction of contracts.

Facts

The appellants (the sellers) are joint venture participants in the Gorgon Gas project. The respondents are entities in the Rio Tinto Iron Ore Group and operate iron ore mines in North West, Western Australia. The first respondent (the buyer) agreed to purchase gas over a period of a number of years under a gas sale agreement (the GSA).7 The GSA is a long-term contract, which creates a separate agreement between the buyer and each seller proportionate to the seller's share of gas to be sold to the buyer. The GSA is a 'take or pay' contract.8 The second and third respondents guaranteed the buyer's obligations.

Clause 14.3 of the GSA stipulated that, after a specified number of years,9 either party may initiate a price review of the gas by issuing a price review notice not more than 120 days nor less than 90 days before the price review date. In 2020 the buyer issued a price notice three weeks late, which fell outside this timeframe.

In the primary proceedings, the buyer claimed that the price review notice was effective notwithstanding that it was issued outside the timeframe. The primary judge found in their favour.10 Alongside textual and purposive considerations, the primary judgment considered whether the parties objectively intended the time stipulation found in clause 14.3 to be essential. The judgment noted that the factors of significance were:11

  1. the way in which 'Price Review Notice' is defined, so as to exclude the time stipulation, when that term is read into clause 14.5;
  2. the purpose of clause 14;
  3. the limited termination rights in the context of a take or pay contract;
  4. the absence of a deeming provision setting out the consequences of non-compliance with the time stipulation; and
  5. the uncommerciality of a construction of clause 14 under which the right to a price review regarding a price review date may be lost simply by a failure to issue the notice within the timeframe stipulated in clause 14.3.

The appellants appealed on the grounds that their opposing construction should be preferred, and the words 'not more than 120 days nor less than 90 days prior' should be construed as being essential.

Judgment

The key question in this appeal was whether the time stipulation in clause 14.3 was essential. The court and the parties agreed this was a question of construction. In considering this, the court outlined the following principles of construction of written contracts from previous case law:12

  • In order to understand the construction of a contract, the court must determine the meaning of the contract's words by reference to its text, context and purpose. Initially, the court must look to the language in the clause and identify all possible meanings of the words chosen by the parties.
  • In doing so, the court should consider what a reasonable person would have understood the terms to mean. The court should consider the language used, the circumstances covered by the contract, and the commercial purpose of the contract.
  • The instrument must be read as a whole and a construction that makes multiple parts of the instrument harmonious is preferable. Each part of the instrument should be construed to have some operation, if possible.
  • The instrument should be given a businesslike interpretation. If there is no clear intention to the contrary, the court should assume the parties intended to achieve a result that makes commercial sense. The terms should therefore be constructed in line with the commercial objective of the instrument, bearing in mind that business common sense may differ among parties.

Proper construction of clause 14

In applying the above principles of construction, the court held that clause 14.3 was the only way in which a party can initiate a price review under the instrument, as any other construction would create disharmony between the provisions within clause 14. The court determined that the parties were sophisticated, well-resourced, and specifically set out provisions that specified set price review dates over a long-term contract. Either party could submit a review within the review period, or it would be held over to the next review period. The court found that it is not unthinkable the parties were aware that if they failed to initiate a price review within the period, they would lose the opportunity to invoke it until the next review period.

Presumption that time is not of the essence

The respondents argued there is a presumption time stipulations in machinery provisions for determining price adjustments under a contract are not essential. The court rejected this argument. It did not accept there is any such general principle applicable to all contracts containing provisions for the adjustment of price, irrespective of the nature, terms, subject matter and market in which the contract operates. Furthermore:

  • the court did not construe clause 14.3 as merely a machinery provision within the context of the contract as a whole; and
  • the court emphasised the distinction between time stipulations for performing obligations (where time is more likely to be of the essence) and time stipulations for exercising rights or powers (where time is less likely to be of the essence)

The task for the court is to discern the intention revealed by the terms of the agreement, and, given the length and detail in the terms:

[the court was] unable to see any principled basis on which the court should approach the task of objective ascertainment of these sophisticated commercial parties' intentions by reference to a presumption, or with any predilection one way or another as to the parties' intentions.'13

AMA Group Ltd v ASSK Investments Pty Ltd [2021] NSWCA 45

Interpretation of contract – condition precedent

In this case, the NSW Court of Appeal considered whether:

  • a 'Binding Heads of Agreement' was a binding agreement to sell a business, or merely a binding agreement to try to negotiate a sale of business agreement; and
  • whether any sale or agreement was conditional on the approval of the purchaser's board.

The court allowed the appeal, finding that the parties only agreed to negotiate a sale of business agreement and that this obligation was subject to board approval of the purchaser.

This case illustrates the ambiguities that can arise from 'binding' heads of agreement that envisage further agreements and are subject to 'board approval'.

Facts

The parties entered into a 'Binding Heads of Agreement' (HOA) for AMA to acquire ASSK Investments. The relevant clauses of the agreement were:

  • clause 2(b), which stated that the 'parties agree to enter into Business Sale Agreements subject to the terms and conditions set out in' the HOA;
  • clause 6, which provided for AMA to 'carry out a comprehensive due diligence' and, subject to that process, 'the transaction will be recorded in a Business Sale Agreement'; and
  • clause 7(b), which was labelled as a condition precedent and required 'all necessary third party consents, authorisations and approvals being obtained (including the Purchaser's Board approval)'.

After the execution of the HOA, AMA completed a due diligence process. It concluded that the deal did not meet the requirements for board approval and terminated the agreement. ASSK Investments sought an order for specific performance and was successful at first instance.

Judgment

The primary issues for the court were:

  1. whether the HOA was an agreement to sell the business, or merely an agreement to negotiate a sale agreement; and
  2. whether clause 7(b) was a condition precedent.

President Bell (with whom Justices Leeming and Emmett agreed) allowed the appeal and held that:

  • the HOA comprised an obligation to negotiate a business sale agreement; and
  • clause 7(b) was a condition precedent to that obligation.

On the first issue, the court disagreed with the primary judge's conclusion that the HOA 'legislate[d] comprehensively for the sale and purchase of the Business'. The court noted that the HOA did not identify any material contracts or key personnel, envisaged further due diligence and left open the possibility of further warranties. Any sale was therefore to be effected by a new agreement, not the HOA.

On the second issue, the court stated that clause 2 made it explicitly clear that the agreement was conditional upon the terms and conditions set out in the agreement. One of those conditions was the approval of AMA's board. The condition was not satisfied and AMA was therefore entitled to terminate the agreement.

In response to an argument that this conclusion would make the promises in the HOA illusory, the court observed that where a contract affords one party a discretion, or where a contract is subject to a party's approval, there is usually an implied requirement for the benefiting party to act honestly, and sometimes reasonably, in exercising that power. However, there was no issue before the court as to the honesty or reasonableness of the board's decision.

CS Energy Limited v GPS Power Pty Limited & Ors [2021] QCA 194

Approach to construction of defined terms in a complex commercial contract

In this case, the Queensland Court of Appeal considered an appeal relating to the construction of a key clause of a commercial contract that involved the use of a defined term.

The court held that, given the complexity of the defined term in question, the primary judge did not err in approaching the construction of the relevant clause by carefully considering which aspects of the defined term were applicable, having regard to the context and purpose of that particular clause.

This case sounds a significant cautionary note for parties who rely on lengthy, multi-faceted defined terms in their contracts. It cannot be automatically assumed that the entirety of a defined term will apply in each instance in which it is used where the contract ascribes particular meaning to words and phrases with the proviso 'unless the context otherwise requires'. Care should be taken in complex commercial arrangements to define terms as simply and succinctly as possible to ensure that the parties' intentions are given effect.

Facts

The dispute in this case centred on the proper construction of clauses in a long-term contract concerning Queensland's Gladstone Power Station (GPS). The appellant is a Queensland Government owned electricity provider and the 'Nominated Generator' for the GPS under the National Electricity Rules governing the National Electricity Market. The respondents are the owners of the GPS, which is Queensland's largest power station and supplies the state's largest individual user of electricity, the Boyne Aluminium Smelter.14

The relationship between the appellant and the respondents regarding the electricity generated by the GPS is governed by a contract known as the Interconnection and Power Pooling Agreement (IPPA).15

Under the IPPA, the appellant is required to purchase electricity generated from the respondents' operation of the GPS to power the smelter; however, the appellant is entitled to trade for profit any excess generated. The ability of the appellant to do so is necessarily dependent on coal availability.16

The appellant contended that the respondents failed to procure and maintain a coal stockpile in accordance with their obligations under the IPPA, compromising the benefit that the appellant was entitled to under the contract.17

The IPPA has a number of defined terms. Clause 1.1 of the IPPA provides that words and phrases used in the contract have the meaning ascribed to them in the annex to the contract, unless the context requires otherwise.18

The main issue on appeal was whether the primary judge erred in construing clause 23 of the IPPA, which addresses the procurement and management of coal, by failing to fully apply the defined term 'Station Annual Forecast' in interpreting that clause.19

The appellants contended that, in accordance with the definition of that term in the annex, 'Station Annual Forecast' includes the upper and lower annual estimates of dispatch of GPS.

Considering the text, context and purpose of clause 23, the primary judge reasoned that the reference to 'Station Annual Forecast' did not include those upper and lower estimates.20

The appellant urged the Court of Appeal to declare otherwise, arguing that that the primary judge neglected to follow the 'orthodox' approach to defined terms.21

Judgment

The court rejected the appellant's appeal.

It acknowledged that the correct approach to the construction of the parties' contract must reflect its commercial character, and did not refute the appellant's general contention that the 'orthodox' approach to defined terms in the context of negotiated commercial contracts is to confer upon them the meaning that the parties have agreed.22

However, the court held that the so-called 'orthodox' approach was not applicable in this case, having regard to the following factors:

  • The IPPA 'is a complex commercial arrangement between sophisticated parties and was drafted with the assistance of experienced lawyers'23
  • the defined meaning of 'Station Annual Forecast' only applies if the context does not otherwise require24
  • the definition of the term 'Station Annual Forecast' is unusual and has many parts. The term is defined as 'a forecast containing [prescribed] material'. As such, it is possible that if some of the material in the forecast is not relevant to the purpose of a particular clause, the term Station Annual Forecast might apply to the clause without regard to information that is irrelevant to that clause25

As a result, it was appropriate for the trial judge to approach the use of the defined term 'Station Annual Forecast' in clause 23 by asking whether the context and purpose of that clause required the use of that term to include the upper and lower estimates, and it was reasonable for the trial judge to conclude that it did not.26

Summarising the conclusion reached, Justice Mullins (who delivered the leading judgment) said at [122]:

The short answer to the appellant's submission that the primary judge failed to apply the orthodox approach to the use of the defined term is that the definition of Station Annual Forecast was not an orthodox definition that was amendable to the orthodox approach of substituting the full meaning for the defined term without considering the nature of the defined term and whether the context required otherwise than the incorporation of all the pieces of information included in the defined term.

The court's ruling on this point was unanimous27 and provides useful guidance to commercial parties on the use of defined terms.

Ulladulla Creative Images Pty Ltd v Tibbles [2021] NSWCA 289

Whether monies received from an insurance claim by the company are payable to former shareholders under a share sale agreement

In this case, the NSW Court of Appeal considered whether former shareholders of a company were entitled, under a share sale agreement, to monies received by the company for losses not covered by its insurance policy.

The court held that, on its construction, the uninsured losses were payable to the respondents under the share sale agreement.

This case illustrates the use by courts of evidence of 'surrounding circumstances' when interpreting ambiguous clauses, and the difference between admissible evidence of surrounding circumstances and inadmissible evidence of the parties' expectations.

Facts

The respondents entered into a share sale agreement (the agreement) to sell their shareholdings in the appellant. Clause 15 of the agreement related to an insurance claim that the appellant had made under its insurance policy with its insurer, QBE Insurance (Australia) Ltd (the policy and QBE, respectively), for damage and loss of business that it suffered from a fire originating from a neighbouring property. The clause provided:

  • 15.1: The Company has made a claim against the Company's Insurers for loss arising out of a fire that took place in the premises known as Unit 83 Collers [sic] Road, Ulladulla, being Lot 18 in Strata Plan 82760 (the 'Premises').
  • 15.2: The Company agrees that if it receives any further money from the Insurance Company beyond those monies received up to the date of this Agreement then any such monies shall be divided equally between the shareholders Debbie, Ian, Karen and John paid to each of the parties within seven (7) days from the date of the receipt of any such monies of the Insurance Company.

Between the time of the fire and entering into the agreement, the appellant made two claims with QBE under its policy, one for property damage and one for business interruption insurance. The appellant also pursued another claim to recover uninsured losses against the owner of the neighbouring property where the fire originated. The neighbour was also insured by QBE. While the amount received from the policy was distributed (or agreed to be distributed) equally in accordance with clause 15.2, the amount received from the appellant's uninsured loss claim was not.

Judgment

Interpretation of clause 15

The court applied the reasoning in Toll (FDCT) Pty Ltd v Alphapharm Pty Ltd (2004) 291 CLR 165 that the 'meaning of the terms of a contractual document is to be determined by what a reasonable person would have understood them to mean', which 'normally, requires consideration not only to the text, but also of the surrounding circumstances known to the parties, and the purpose of the transactions'. In doing so, the court noted that:

  • the purpose of the agreement was to sell a small business that had recently been impacted by a fire;
  • the parties were commercially unsophisticated;
  • the parties did not possess specialised knowledge of an insurance 'claim'; and
  • the respondents did not have oversight of the appellant's insurance claim.

For these reasons, the court construed the plain words of the clause to include any amounts paid by QBE as a result of the claim against the neighbour. In reaching this conclusion, the court:

  1. had regard to the fact that the appellant had asked QBE (as its insurer) to bring a subrogated claim against the neighbour, as this evidence was admissible to explain the phrase 'claim against the Company's insurers' in clause 15.1; but
  2. did not have regard to a file note of a solicitor (allegedly) recording the parties' expectations as to how such recoveries might be distributed.

The uninsured losses were therefore required to be paid in accordance with clause 15.2 to the respondents.

In reaching this conclusion, the court accepted that clause 15.1 had no operative effect and acted as a recital to clause 15.2. However, that did not mean clause 15.1 was redundant, because it aided in the interpretation of clause 15.2 by limiting 'further money' to the fire described in the clause. The absence of clause 15.1, read literally, would require the appellant to pay out any money that it received from its insurance provider at any point for any event.

Footnotes

  1. [2021] NSWCA 332.

  2. [2021] QCA 156.

  3. [2021] WASCA 193.

  4. [2021] NSWCA 45.

  5. [2021] QCA 194.

  6. [2021] NSWCA 289.

  7. Specific number of years redacted in judgment.

  8. A 'take or pay' contract provides protection for a seller by requiring the purchaser to either take delivery of the product from the supplier or pay a penalty if they fail to do so.

  9. Specific number of years redacted in judgment.

  10. Pilbara Iron Company (Services) Pty Ltd v Chevron (TAPL) Pty Ltd [2020] WASC 296.

  11. Chevron (Tapl) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd [2021] WASCA 193, [34].

  12. Black Box Control Pty Ltd v TerraVision Pty Ltd [2016] WASCA 219; Sino Iron Pty Ltd v Mineralogy Pty Ltd [2019] WASCA 80; (2019) 55 WAR 89.

  13. Chevron (Tapl) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd [2021] WASCA 193, [284].

  14. CS Energy Limited v GPS Power Pty Limited & Ors [2021] QCA 194, [19].

  15. Ibid, [14].

  16. Ibid, [24]-[25].

  17. Ibid, [26].

  18. Ibid, [14], [85].

  19. Ibid, [99].

  20. Ibid, [103]-[107].

  21. Ibid, [28], [32], [116].

  22. Ibid, [79], [84].

  23. Ibid, [79].

  24. Ibid, [118].

  25. Ibid, [119].

  26. Ibid, [120]-[123].

  27. Note that Justice McMurdo delivered a separate judgment, agreeing with Justice Mullins on all issues but one relating to the utility of declarations sought by the appellant concerning the calculation of the coal stockpile. Justice Fraser agreed with Justice Mullins.