INSIGHT

Long-awaited NSW Renewable Energy Planning Framework delivers greater certainty for renewable energy projects

By Naomi Bergman, Lydia Watson-Moore, Alexander Murphy
Energy Energy regulation Environment & Planning Renewable Energy

Significant new guidance for renewable energy industry 20 min read

The NSW Government has released the final version of its new Renewable Energy Planning Framework (Framework), nearly a year after the draft Energy Policy Framework (Draft Framework) was released for public comment last November.

The new Framework has been welcomed by industry as a generally positive step. While it requires a higher level of environmental assessment in some respects, and is more prescriptive about the matters to be addressed in agreements with landowners compared to the previous guidelines, it offers greater certainty and transparency for communities and landowners, which will potentially assist developers with securing and maintaining 'social licence'.

In this Insight, we set out the key differences between the new Framework and the previous guidelines, highlighting the implications for the assessment of renewable energy projects and landowner arrangements, as well as the amendments made in response to feedback on the Draft Framework.

Key takeaways

  • The NSW Government has said the new Framework will support faster, more consistent decisions and greater investment certainty. Given that NSW currently has the slowest approval times for renewable energy projects in Australia, this is welcome news for the industry if achieved.

  • While the Framework is identified as 'guidance', the Guidelines state that applicants will have to comply with the Framework as a requirement of their Secretary's environmental assessment requirements (SEARs).

  • Aspects of the Framework will commence immediately, and may affect the assessment of impacts and negotiation with landowners for projects currently under assessment. The Wind Energy and Large-Scale Solar Energy Guidelines will also apply to modifications of existing state significant developments (SSD) consents.

  • Applicants are expected to identify which landholders are associated or non-associated with a project when submitting a Scoping Report, meaning applicants will need to negotiate private agreements very early on in the development process. This may be challenging in circumstances where agreements are expected to clearly identify the scope of impacts that will be experienced at a dwelling, but applicants will not have prepared detailed noise, visual and other assessments to be able to accurately identify the likely impacts at the Scoping Report stage.

  • A setback distance for turbines from dwellings has now been prescribed, and an upper noise limit for adverse health impacts has also been suggested.

  • Applicants will be required to assess a project's impacts on vacant land with 'development rights', but only in certain circumstances and the level of assessment required is more limited than that required for existing dwellings. Significantly, the Framework clarifies that dwellings that have been approved but not yet constructed as at the SEARs issue date do not need to be treated as existing dwellings for the purpose of the visual impact assessment or noise assessment, unless the consents for those dwellings have been physically commenced as at that date.

  • The Framework includes a commitment by government to make every effort to assess large-scale solar energy applications within 100 government days.

  • The Framework stipulates expected benefit-sharing rates for solar, wind and battery energy storage system (BESS), to be provided above and beyond the compensation already payable to host landowners and neighbours.

  • The Framework includes estimated decommissioning costs for wind turbines ($480,000 per turbine) and solar panels ($52 per panel) and suggests landowners may wish to seek security for these costs in private agreements.


Background

In November 2023, the NSW Government released the Draft Framework for public comment. In our previous Insight, we outlined the key aspects of the Draft Framework and its component documents. As noted in that Insight, industry had a number of concerns in relation to the Draft Framework and the potential for it to make it more difficult to obtain approval for new projects, particularly new wind energy developments.

In response to extensive industry feedback, the NSW Government has made several changes to the Draft. While the final Framework is a significant improvement, it does not entirely address some of the tensions in the planning assessment of renewable projects, as outlined below.

Key changes from the Draft Framework

  • The Private Agreement Guideline no longer includes a full-form template neighbour agreement, but rather a handful of suggested 'model clauses'. This is a positive change, as many stakeholders in the industry were concerned about the content of a number of clauses in the template agreement.
  • Transitional provisions for the commencement of the Framework have been clarified, however a different approach has been taken for each type of renewable project (discussed further below). The Draft Framework did not include transitional provisions for the Private Agreement Guideline—these have now been included.
  • A new concept of 'development rights' has been introduced to replace what was previously described as 'dwelling entitlements'. Applicants will still need to undertake a degree of assessment of impacts on the development potential of vacant surrounding land, however the circumstances in which an assessment of impacts on a vacant lot have been clarified and the requirements are less extensive than what was proposed in the Draft.
  • The prescribed setback distance for wind turbines has been reduced (from 2km to 1.5km).
  • The Benefit Sharing Guideline now also includes a benefit sharing rate for standalone BESS developments.

 

When do the changes apply?

When the Framework begins to apply to existing projects varies depending on the type of development.

Wind developments:

  • Subject to one caveat, the Framework (including the Benefit Sharing Guideline and Private Agreement Guideline) does not apply to any development application (DA) for which an Environmental Impact Statement (EIS) has already been lodged prior to 12 November 2024 or, if SEARs were issued prior to 12 November 2024, where an EIS is lodged before 30 April 2025.
  • For applicants who are currently preparing an EIS for a project, this means the project must already have SEARs and the EIS must be lodged prior to 30 April 2025 to be considered under the old guidelines.
  • However, the 'development rights' aspect of the Framework applies immediately to all projects for which an EIS had not been lodged as at 12 November 2024.

Solar developments:

  • The visual impact assessment requirements apply immediately, though the Department of Planning, Housing and Environment (Department) does not expect all visual impact assessments (VIAs) to be updated (given the changes reduce the amount of work required).
  • The Benefit Sharing Guideline does not apply to any DAs for which an EIS has been lodged prior to 12 November 2024 or, if SEARs were issued prior to 12 November 2024, where an EIS is lodged before 30 April 2025.
  • All other aspects of the Framework, including the 'development rights' provisions and the Private Agreement Guideline, apply immediately.

Transmission and BESS developments:

  • The Framework does not apply to any DAs for which an EIS has been lodged prior to 12 November 2024 or, if SEARs were issued prior to 12 November 2024, where an EIS is lodged before 30 April 2025.

While the Framework is identified as 'guidance', the Guidelines state that applicants will have to comply with the Framework as a requirement of their SEARs. The Wind Energy Guideline and Large-Scale Solar Energy Guideline state that applicants must also consider these guidelines when preparing and assessing applications to modify an SSD consent for those types of developments.

Key aspects of the new Framework

Wind Energy Guideline

Consistent with the Draft Framework, the new Wind Energy Guideline suggests applicants should include a constraints map in their Scoping Report which, amongst other things, identifies which residences will be associated with the project and which are non-associated. This appears to envisage that applicants will have entered private agreements (including both neighbour and host landowner agreements) with relevant landowners prior to the Scoping Report stage.

This gives rise to a key tension within the Framework documents. As discussed further below, the new Private Agreement Guideline notes that agreements should clearly identify the scope of any impacts that a particular landowner will experience as a result of the development. However, applicants are typically at a very preliminary stage of planning when submitting a Scoping Report, having not yet finalised the project design or undertaken detailed noise and visual impact assessments. It is therefore difficult to accurately predict the impacts at any particular residence at that stage of the process.

This requires applicants to walk a difficult line when negotiating with landowners, needing to provide as much detail as possible but also being careful not to misrepresent what the impacts will be. Both overstating and understating the potential impacts in early discussions with landowners could be damaging. The Framework does acknowledge that private agreements may be entered after submitting an EIS, but that where this occurs, the consent authority should be notified at the earliest opportunity.

Another one of the more controversial aspects of the Draft Framework that has been retained in the new Wind Energy Guideline, albeit with welcome variations, is the requirement to assess impacts on properties with 'dwelling entitlements' (although these are now referred to as 'development rights'). These are rights of neighbouring landholders to develop their vacant land for the purposes of residential accommodation, tourist and visitor accommodation, and eco-tourist facilities. Under the finalised Guideline, assessment of a project's impacts on development rights is only required if the land would be within the visual impact setback (1.5km), experience exceedances of noise criteria, or be subject to significant risks from blade throw, ice throw or other risks.

In a further welcome development for industry, the assessment of impacts on properties with development rights does not need to be as detailed as that required for existing dwellings (ie no need for a full visual impact assessment). Rather, Appendix B of the new Guideline provides an example assessment, which is a desktop analysis of matters such as the size of the lot, slope, degree of vegetation, etc.

Importantly, the new Guideline also clarifies that dwellings that have been approved but not yet constructed as at the date SEARs are issued for a project do not need to be treated as existing dwellings for the purpose of the visual impact assessment or noise assessment, unless the consents for those dwellings have been physically commenced as at that date. However, the Guildeine states that applicants should still consider measures to mitigate impacts on vacant land that is subject to a DA that is yet to be determined or has been approved but not yet physically commenced.

Also of note, the final Guideline:

  • no longer mentions that the addition of battery storage to an existing wind or solar development may be achieved by way of a modification application—this was a helpful inclusion in the Draft Guideline that has now been removed.
  • confirms that the Minister will consider requests to declare a wind energy development as critical state significant infrastructure (CSSI) if it includes a significant energy storage system (eg a battery with a power capacity of 750 MW), which potentially opens a more streamlined approval pathway.
  • includes the same 30 hours a year limit for shadow flicker, though the Guideline explicitly acknowledges this can be exceeded where agreed in a Private Agreement (which was already the case).
  • requires applicants to model the number of hours of potential shadow flicker at or within 50m of an affected dwelling or at other sensitive land uses, but only for non-associated residences. This differs from the Draft Framework, which had suggested that shadow flicker modelling must be undertaken for all turbines for both associated and non-associated residences. That said, in practice we expect some degree of modelling or assessment will need to be undertaken for all nearby dwellings to ascertain whether the 30 hours a year limit will be met, or the dwelling will require a Private Agreement, however the modelling for associated residences will not need to be presented in the EIS.
  • unlike the Draft Framework, now explicitly mentions that s7.11 local infrastructure contributions will generally not be payable for wind energy projects. While s7.12 contributions may be payable if a contributions plan is in place, the Guideline states that issues like road upgrades should be dealt with through conditions of development consent, rather than contributions or planning agreements. Additionally, if a benefit-sharing rate will be paid (under the Benefit Sharing Guideline), the Guideline helpfully acknowledges that local contributions should not be required.

The Technical Supplement for Noise Impact Assessment (Noise Supplement), which accompanies the final Wind Energy Guideline, is largely similar to the existing Noise Bulletin that it will replace, and is also largely consistent with the version in the Draft Framework.

Of note, the Noise Supplement:

  • continues to apply the South Australian noise guidelines, including a 35dB(A) general limit, though it emphasises that landholders can accept noise greater than this limit. If an agreement is in place with a landholder, it confirms that a noise impact assessment is not required for that landowner (though an indicative noise assessment will be required for the Scoping Report that assesses all receivers and, in practice, some modelling will be required for the applicant to properly scope the noise impacts that will be experienced by landholders in the relevant Private Agreements).
  • now identifies that noise caused by a wind energy project should not exceed 50dB(A) in national parks (a criterion it says will be typically achieved at a setback distance of 500m).
  • identifies 37dB as an 'appropriate maximum noise level limit' to mitigate annoyance for residents, although acknowledges that landholders may accept higher levels in private agreements. This perhaps unhelpfully suggests that noise levels over 37dB may cause annoyance or disturbance, when this is not necessarily the case. In fact, for helpful context, the overview to the Framework notes that 35dBA is equivalent to sound levels in a quiet library and less than a household refrigerator.

The Technical Supplement for Landscape Character and Visual Impact Assessment (Visual Supplement) is notably more detailed than the existing Visual Bulletin it will replace. There have also been some key changes from the version in the Draft Framework.

As discussed above, a notable change from the Draft Framework is the introduction of the concept of 'development rights' instead of 'dwelling entitlements'. Under the Draft Framework, applicants would have been required to undertake visual impact assessments for dwellings that not only were already in existence or were subject to DAs lodged (but not determined), but also to assess any parcel of land for which a DA could be made for a dwelling (ie land with a 'dwelling entitlement'). While the same concept has been retained, the extent of visual impact assessment required is more limited than under the Draft Framework and is only required in the limited circumstances noted above.

Other key things to note include:

  • Unlike the current Visual Bulletin which does not impose any minimum setback, the new Visual Supplement specifies a setback distance of 1.5km for a 240m turbine from any dwelling, with a sliding scale of lesser and greater setback distances for turbines of lesser and greater height respectively. Notably, these distances have been reduced from those included in the Draft Framework (which required a 2km setback from a 250m turbine) but are still greater than the 1km setback requirement in Victoria. However, it is clear that landowners can accept a turbine within this setback distance under a private agreement.
  • The Visual Supplement includes a lot of reference imagery, including diagrams and images, which may be helpful to applicants to provide greater certainty and clarity of expectations in a traditionally subjective assessment. It also has an increased focus on the use of photomontages.
  • Consistent with the Draft Framework, the Visual Supplement states that turbines remain a prominent feature of the landscape between 2km and 8km away, and will be noticeable up to 12km away.
  • An EIS must include a separate landscape character assessment, with a study area of approximately 25km from the proposed development, in addition to a visual impact assessment, though applicants can seek to justify a smaller area if appropriate.
  • The Draft Framework identified that a dwelling may have more than one primary view, but the final Visual Supplement helpfully states that only one primary view is required to be identified for each dwelling in the detailed assessment and all other views must be considered secondary.
Transmission Guideline

The Transmission Guideline is largely similar to the version in the Draft Framework, although it now defines 'new major transmission projects' to which the Framework applies as meaning 'energy transmission projects that are declared as SSI or CSSI'. It was previously unclear what was meant by major transmission projects.

Like the Draft Framework, the new Framework includes a Technical Supplement for Landscape and Visual Impact Assessment for transmission projects, which requires a setback from dwellings that varies depending on tower height (eg 370m for an 80m tower). However, consistent with the other supplements, the requirement to consider dwelling entitlements has been removed and impacts on proposed dwellings with development consents that have not been physically commenced are no longer required to be assessed in a visual impact assessment. Unlike the other supplements, there is no requirement to consider impacts of major transmission projects on properties with 'development rights'.

Large-scale Solar Energy Guideline

When the Draft Framework was released last year, an updated version of the Large-scale Solar Energy Guideline had not yet been prepared, though proposed updates were foreshadowed in the overview to the Draft Framework. Most of those changes have now been incorporated into the Guideline, with some exceptions.

The most notable development is that the Guideline now includes a commitment by government to make every effort to assess large-scale solar energy applications within 100 government days. While there may be some uncertainty as to what constitutes a 'government day' (this term is not defined), this will be very welcome news for applicants.

Also of note, the new Guideline:

  • does not include a map identifying desirable, suitable and less suitable sites for solar developments, despite this being foreshadowed in the Draft Framework (likely due to the controversy caused by the map that was included in the initial draft Wind Energy Guideline).
  • confirms that the Minister will consider requests to declare a large-scale solar energy development as CSSI if it includes a significant energy storage system (eg a battery with a power capacity of 750 MW).
  • like the new Wind Energy Guideline, helpfully identifies that local infrastructure contributions will generally have little or no application to large-scale solar energy projects.
  • identifies that the cost of decommissioning solar panels is estimated to be around $52 per panel (inclusive of recovery costs), which may provide useful guidance when negotiating landowner agreements that include security for decommissioning costs.
  • incorporates the new Benefit Sharing Guideline and Private Agreement Guideline (discussed below) and omits the equivalent provisions that had been in the old Solar Guideline.
  • introduces the same assessment requirements for 'development rights' discussed above, but only in respect of vacant land that immediately adjoins the development or that will experience exceedances of noise criteria.
Benefit Sharing Guideline

The finalised Benefit Sharing Guideline is largely consistent with the version in the Draft Framework. It expresses an expectation that applicants will provide benefit-sharing programs at a rate of $850 per megawatt per annum for solar energy developments, and $1050 per megawatt per annum for wind energy developments, based on installed capacity and paid over the life of the development (indexed to CPI).

Notably, a new benefit-sharing rate of $150 per megawatt hour (which was not in the Draft Framework) has also been introduced for standalone BESS developments located in rural zones. This rate will not apply to BESS projects that are delivered as part of a wind or solar energy development.

Other points to note include:

  • The Guideline indicates that benefit-sharing programs must include benefits at both the neighbourhood and local community level, with benefits for neighbours to be separate to any mitigation measures or payments being provided to neighbours under private agreements.
  • The benefit-sharing will not necessarily have to be entirely in the form of a monetary contribution. Applicants may be able to structure the contribution in different ways (such as providing direct capital works), provided the overall value is equal to the nominated monetary amount.
  • Applicants will need to outline the proposed community benefit-sharing arrangements for the project in their EIS, including the expected total value of benefits they will pay. The Guideline suggests that as a general guide, no less than 85% of the total benefit-sharing value should be administered by the relevant council(s).
  • The Guideline also states that the total value of benefit-sharing should not exceed the rates identified above. Accordingly, while the new rates will no doubt in practice form a baseline that councils will expect to receive as a matter of course, the rates will also act as a ceiling and should assist applicants to resist requests for higher amounts.
Private Agreement Guideline

One of the most significant aspects of the Draft Framework was the introduction of a 59-page Private Agreement Guideline that was to replace the existing one page of 'minimum standards' for neighbour agreements in the 2016 Wind Energy Guideline. The draft included a template 'impact agreement' that could be used for both host and non-host landowners. Industry provided extensive feedback about this template, with concerns raised about the suitability and appropriateness of having a template, as well as the content of many of the clauses.

The final Private Agreement Guideline does not include a template agreement—this has been replaced with general guidance on matters that should be addressed in agreements and a select number of 'model clauses'. This guidance applies to both host landowner documents as well as non-host agreements (now described as 'neighbour agreements', rather than 'impact agreements' as per the Draft Framework).

The majority of the previous 'minimum standards' for neighbour agreements have been brought across to the Private Agreement Guideline with some new additions, although these are no longer described as 'minimum standards'. Rather, the document is framed as general guidance that applicants should consider when negotiating any host and neighbour agreements. That being said, landowners will likely expect any new agreements for projects covered by the Framework to address the matters in the Private Agreement Guideline and it may in practice be difficult to depart from the model clauses, even though these are not expressed as being mandatory.

A key difference between the final Guideline and the version in the Draft Framework concerns the degree to which impacts must be scoped in an agreement. The Draft Framework required that impacts be 'fully particularised' in an agreement, including likely noise levels at different times of the day and photomontages to reflect visual impacts. The final Guideline no longer includes these requirements, perhaps in recognition of the tension referred to above that arises from the evident desire for landowners to be both signed up early in the process, at a stage when only preliminary assessments are typically available, and also to be well-informed of the impacts they will experience.

The key differences between the current 'minimum standards' for landowner agreements and the requirements in the new Guideline include:

  • Agreements should make provision for circumstances where the project is materially delayed, or the scope or scale of the project materially changes—the Guideline states that agreements should include a clause that triggers a review of compensation in the event of material changes.
  • Agreements should specify that the applicant is responsible for monitoring project impacts and specify how the impacts will be monitored, how often and how the landholder will be provided the results. The agreement should also contain provisions regarding land access for monitoring.
  • Host landowner agreements should outline biosecurity protocols and measures the applicant will take on the property to manage biosecurity risks.
  • A register of agreements is to be provided to the Department when the EIS is submitted that outlines each agreement, what impacts are excluded and the duration of those impacts. The draft Guideline suggested copies of all agreements would need to be submitted to the Department, however this has now been replaced with the register concept. This is a welcome development that will avoid applicants having to disclose commercially sensitive terms of agreements, such as the extent of compensation payable.
  • Key information about the project is to be given to the landowner after signing, including an indication of the extent of the development on the site, details of likely impacts, likely start date and duration of works. Information should be provided to landholders at key milestones during the project.

The new model clauses in the Guideline cover the following matters:

  • Confidentiality: while the Draft Guideline had suggested that landowners should not accept confidentiality clauses, the final Guideline acknowledges that confidentiality clauses can benefit both parties. The model clause suggests that only certain information should be confidential, rather than the entire agreement.
  • Landholder's right to participate in the planning process: the Guideline suggests agreements should include a clause that acknowledges the landholder's continued right to participate in engagement about, and make submissions in relation to, the development (provided the submission does not constitute an objection), and correspond with authorities if the applicant does not comply with consent conditions.
  • Compensation: this model clause is a very basic compensation clause which, in our view, will need to be adapted in each agreement.
  • Dispute resolution: the model dispute resolution clause provides for mediation processes prior to court proceedings, which is standard in these agreements.
  • Other landholder obligations: this clause provides that the landholder may allow access for the purpose of mineral exploration, surveys and field work for major transmission projects, and operation of other electricity generating equipment for private domestic use. The Guideline expressly states that a private agreement cannot restrict access or use of land for minerals exploration.
  • Decommissioning: the Guideline suggests landowners may wish to ask for security for decommissioning costs in the form of a bank guarantee. The Guideline also suggests the cost of decommissioning a wind energy project is around $480,000 per turbine.

We anticipate that the model clauses in the Guideline will form a starting point for negotiations with landowners going forward and applicants may need a strong justification to depart from the Guideline.